With the increasing application of concrete, investing in concrete batching plant has become a good project, but before investing, customers must have an in-depth understanding of the concrete batching plant. Today we will take a look at the working process of concrete batching plant. In fact, there are total four steps of working process for concrete batching plant.

The Working Process of Concrete Batching Plant

The process of putting raw materials into the weighing hopper

Aggregate feeding

Opening the corresponding aggregate bin valve according to the formula → weigh → open the weighing hopper door → end of feeding → close the weighing door → conveyor belt to the waiting bin, this process starts the vibration machine at the same time, and the feeding ends The aftershock machine is turned off after a delay of 1S.

Cement feeding

select cement silo → start feeder → weighing according to the formula. This process manually breaks the arch as required.

Powder feeding

select ore powder silo or fly ash silo according to the formula → start feeder → weighing . This process manually breaks the arch as needed.

Admixture feeding

start the feeder → weigh → open the weighing hopper valve → end the feeding → close the weighing door → send the conveyor belt to the waiting silo. In this process, the weighing hopper is shaken by a pneumatic hammer. After the end of the feeding Delay the closing of the shock pump valve.

Water feeding

start the water pump → weigh

The Process of Feeding Which Going to Waiting Bin by Belt Conveyor

In the process of feeding, the feeding time of each aggregate should be delayed to a certain extent to prevent the belt from overloading. Normal shutdown needs to be stopped along the material flow, and both belts will stop during emergency stop.

The Process of Putting Everything to Mixer

After all, check whether the discharge door of the mixer is closed, open the waiting silo→powder silo→aqueous agent silo valve and put it into the mixer. The injection time of the aquatic agent should be a little earlier than other materials. There is a vibration machine on the waiting silo.

The Process of Mixing

After mixing all the materials, start mixing → end of mixing → unloading. If the production is cycled, the mixing will be carried out at the same time as the feeding and feeding work. After the unloading is completed, close the mixer discharge door.

Rate this Article:
Previous: Things Need to Prepare Before Build a Concrete Batching PlantNext: Operating Concrete Batching Plant in Winter

Contact Us

Camelway answers all your questions 24 hours a day.

Your personal information will be kept confidential

Leave a message

Leave a message

Your personal information will be kept confidential